Over the next 2 weeks, crews will be doing a leaf collection test run in select areas to test equipment functionality. This is not the official leaf pickup. A second, formal pass will follow later to collect leaves properly. The official leaf collection programs begins November 10. Thank you for your patience while we fine-tune the process.
Town of Manchester Newsletter for Important Town News, Information, and Events.
The Town of Manchester Department of Public Works, Engineering Division proposes the replacement of two existing traffic control signals and minor roadway work at the intersections of 1) Middle Turnpike West at Tower Road and 2) Middle Turnpike West at Green Manor Boulevard (Private Road). Project also includes other appurtenant work such as the installation of concrete sidewalks and ramps, minor storm drainage construction, bituminous concrete milling and resurfacing, installation of pavement markings, and restoration of lawn areas.
Advance Traffic Control features to be included are:
This project is funded through the Department of Public Works 2015 Bond Referendum and 2019 Bond Referendum.
Middle Tpke W & Tower Rd, Manchester, CT 06045 View Map
Middle Tpke W & Tower Rd , Manchester, CT 06045
Eng. Division Inspectors:
Scott SobinskiChief Construction Inspector Telephone: (860) 614-5464
Eng. Division Design:
Jim Mayer, P.E.Traffic Engineer Telephone: (860) 647-3151
John E. DiBiasi, P.E.Assistant Town Engineer Telephone: (860) 647-3154