Streetlight Improvements - Ambassador Dr and Esquire Dr

  • Project typeStreetlights
  • Project value$150,000
  • Project scheduleApril 2026 to July 2026
  • Contractor nameTown Staff/Turri/Eversource
  • Completion DateJuly 31, 2026
lightimage.jpg

Project will replace the existing streetlights, poles and electrical service for streetlights on Ambassador Drive and Esquire Drive.  Construction will be a joint effort between Town Field Services Staff, Eversource and the Town's streetlighting contractor, Turri Inc.  

Phase 1 (April/May):  Town staff will install new conduits for new streetlight service.

Phase 2 (June):  Town staff and Turri Inc. will install new fiberglass streetlight poles and LED lights.

Phase 3 (July):  Eversource will install new electrical conductors to energize new lighting system.   Town staff will remove old wooden poles and lights once new system is operational.