Over the next 2 weeks, crews will be doing a leaf collection test run in select areas to test equipment functionality. This is not the official leaf pickup. A second, formal pass will follow later to collect leaves properly. The official leaf collection programs begins November 10. Thank you for your patience while we fine-tune the process.
Town of Manchester Newsletter for Important Town News, Information, and Events.
This project includes construction of concrete sidewalks on the south side of Deming Street and on the north side of Tolland Turnpike (State Routes 30 and 83) between Hale Road and the Vernon town line.
Project is 100% state funded through the Local Transportation Capital Improvement Program (LOTCIP) of the CT Dept. of Transportation.
Schedule:
Design and Permitting: Fall 2025/Winter 2026
Construction: Summer 2026
Deming St and Tolland Tpke, Manchester, CT 06042 View Map
Deming St and Tolland Tpke , Manchester, CT 06042